Final two pandemic-delayed BTO projects completed: HDB

The two Build-to-Order (BTO) plans, Punggol Point Cove (Phase 2) and Kempas Residences, note the completion of HDB’s pandemic-delayed real estate projects. As a whole, the 92 plans have supplied over 75,800 new condos to Singaporeans over the last five years.

Midtown Bay condo

At present, 110 HDB housing projects are under development, up from 95 a year ago due to the increase in BTO supply in recent years. HDB says it is on track to complete around 17,000 flats all around 27 projects in 2025.

As at Jan 15, 37 households or about 7% of 555 booked units have collected their keys.

HDB is assumed to inform the remaining flat proprietors of their key collection date shortly, following the completion of the final blocks among both projects this month.

Apartment proprietors of Punggol Point Cove (Phase 2) have actually been getting the keys to their brand-new residence since November 2024, while key collection for Kempas Residence started in mid-January this year.

According to HDB, the conclusion of Punggol Point Cove (Stage 2) denotes the completion of all condos in the Punggol Point District. This includes Punggol Point Cove (Phase 1), Punggol Point Woods and Punggol Point Crown BTO ventures, which were finished in 2024.

The remaining ventures had waiting times of as much as 5 years. On the whole, over 18,000 flats were completed in 2024, says HDB.

Minister for National Development Desmond Lee has publicized the finish of the last two pandemic-delayed projects from HDB, according to a Jan 20 launch.

The 22 house projects included 2 Shorter Waiting Time (SWT) ventures, that were finished in just a waiting period of much less than three years. The SWT projects, Parc Glen at Tengah and Grove Spring at Yishun, comprised a total amount of 1,995 condos.

Placed around New Punggol Roadway, Punggol Point Cove (Phase 2) makes up 1,179 units of two-room flexi, three-, 4- and five-room condos throughout six residential blocks. Following pandemic hold-ups, the project’s last block was completed 12 months from its initial Probable Completion Date (PCD) at an earlier time this month.

In 2024, HDB finished a total of 22 housing properties, 17 of which were delayed by the pandemic. With the exception of one that was postponed because of non-pandemic causes, the remaining four house plans were finished promptly.

As at Jan 15, 657 houses or 59% of 1,109 lined up units have gathered their keys.

Positioned in between Serangoon Roadway, Lavender Street and Boon Kheng Road, Kempas Residences BTO project has 583 units of two-room flexi, three-, four-room apartments throughout four residential blocks.

The final block, which was postponed by six months from its original PCD, was completed in mid-January.